Location Macau
Time 2019
Overview
A Macau residential development, Nova Taipa Gardens Phase 5, have utilised the SSME for the inspection of fire service installation for about three months before occupation. A total of 18 gensets were rented, 15 DCA400ESEI gensets units allocated into four groups (four units for Tower 1 to 4, four units for Tower 5 to 8, five units for the Podium and two units for retail) and synchronised to provide electrical power for the inspection of the fire service installation, including emergency lighting, exit signs, firemen's lifts, fire service pumps, fire alarms, etc.